NOASSERTIONupdated 6mo ago
This skill serves as the capstone for construction project management, integrating all trades and coordination skills to deliver a fully commissioned, documented, and turned-over project. Use this skill to navigate the systematic process of verifying building systems, completing punch lists, compiling closeout documentation, and transitioning the project to the owner.
What can you do with Commissioning Closeout?
name: commissioning-closeout description: Guides construction PMs through building commissioning, TAB, punch lists, O&M documentation, warranties, and project closeout.
Commissioning & Closeout Skill
This skill serves as the capstone for construction project management, integrating all trades and coordination skills to deliver a fully commissioned, documented, and turned-over project. Use this skill to navigate the systematic process of verifying building systems, completing punch lists, compiling closeout documentation, and transitioning the project to the owner.
Quick Reference Tables
Commissioning Phases
| Phase | Key Activities | PM Responsibilities |
|---|---|---|
| Pre-Design | OPR development, CxA selection | Support owner, review scope |
| Design | BOD review, Cx specs | Review specifications |
| Construction | Pre-functional, FPT, issues | Coordinate, schedule, track |
| Acceptance | Seasonal testing, final report | Verify completion, acceptance |
| Post-Occupancy | Warranty support, 11-month walk | Callback coordination |
Systems to Commission
| System Category | Key Systems | Reference Skill |
|---|---|---|
| HVAC | Heating, cooling, ventilation, exhaust | [mechanical-plumbing-systems] |
| Electrical | Power distribution, emergency, lighting | [electrical-systems] |
| Plumbing | Domestic water, sanitary, specialty | [mechanical-plumbing-systems] |
| Fire Protection | Sprinkler, fire alarm, smoke control | [fire-protection-systems] |
| Building Envelope | Air barrier, waterproofing, thermal | [building-envelope-exterior] |
| Low-Voltage | BAS, security, AV, nurse call | [low-voltage-technology] |
| Vertical Transport | Elevators, escalators | [elevators-vertical-transportation] |
| Specialty | Kitchen, lab, medical equipment | [equipment-division-11] |
| Sustainable | Solar PV, EV, BESS, geothermal | [sustainable-systems] |
Closeout Milestones
| Milestone | Criteria | Key Deliverables |
|---|---|---|
| Pre-Substantial | Systems operational, Cx near complete | Pre-punch complete |
| Substantial Completion | Occupiable, life safety complete | Certificate of SC, TCO/CO |
| Punch List Complete | All items resolved | Sign-off documentation |
| Final Completion | All work/docs complete | Final CO, final payment |
| Warranty End | 11-month walk complete | Warranty closeout |
TAB Tolerances
| Measurement | Tolerance | Notes |
|---|---|---|
| Supply/Return Air | ±10% of design | Per terminal/zone |
| Outside Air | 0 to +10% of design | Never less than design |
| Exhaust Air | 0 to +10% of design | Never less than design |
| Hydronic Flow | ±10% of design | Per terminal |
| System Total | ±5% of design | Overall system |
Closeout Documentation Checklist
| Document | Responsibility | Timing |
|---|---|---|
| O&M Manuals | Contractor/Subs | Before SC |
| As-Built Drawings | Contractor/Subs | Before FC |
| Warranties | Contractor/Subs | At SC |
| Training Records | Contractor | Before occupancy |
| Commissioning Report | CxA | Before FC |
| TAB Report | TAB Contractor | Before Cx FPT |
| Final Lien Waivers | All parties | At final payment |
Reference Files
Commissioning Fundamentals
- Commissioning Overview - Definition, benefits, phases, team roles, types
- Commissioning Planning - OPR, BOD, Cx plan, specifications, schedule
- Pre-Functional Checklists - Purpose, content, process, by system
- Functional Performance Testing - Process, types, conditions, issues log
System Commissioning
- HVAC Commissioning - Heating, cooling, air handling, exhaust, smoke control
- Electrical Commissioning - Power distribution, emergency power, lighting
- Plumbing & Fire Protection - Domestic water, sprinkler, fire alarm
- Envelope Commissioning - Air barrier, water resistance, thermal
- Low-Voltage Commissioning - BAS, security, AV, nurse call, DAS
- Specialty Systems - Elevator, kitchen, lab, medical, sustainable
Testing, Adjusting, Balancing (TAB)
- TAB Overview - Definition, contractors, certification, specifications
- Air Balancing - Supply, return, exhaust, outside air, tolerances
- Hydronic Balancing - Chilled/hot water, pumps, tolerances
Controls & Integration
- BAS/Controls - Points verification, sequences, graphics, integration
- Integrated Systems Testing - Fire/life safety, smoke control, security
- Emergency Power Testing - Generator, ATS, load verification
Completion & Turnover
- Substantial Completion - Definition, criteria, TCO, warranty start
- Punch List Management - Development, tracking, execution, completion
- Final Completion - Criteria, CO, final payment, lien waivers
- O&M Manuals - Content, format, collection, review
- As-Built Documentation - Red-lines, CAD, BIM, deliverables
- Warranties - Types, documentation, start dates
- Training & Turnover - Requirements, scheduling, attic stock, keys
- Warranty Administration - Period management, 11-month walk, claims
Inspections & Coordination
- Code Inspections & CO - Final inspections, fire marshal, permit closeout
- Coordination & Sequencing - Cx coordination, TAB, closeout schedule
- Specifications & CSI - Division 01 sections, related specs
Integration with Other Skills
Project Management Skills
| Skill | Integration Points |
|---|---|
| [procore-project-management] | Punch lists, documentation, submittals, issue tracking |
| [quality-control-closeout] | QC framework, completion procedures |
| [vdc-bim-coordination] | As-built models, COBie, BIM integration |
| [schedule-management-cpm] | Closeout schedule, milestones, critical path |
| [contract-administration] | Substantial/final completion, retainage, payments |
| [subcontractor-management] | Sub closeout, lien waivers, warranty coordination |
| [owner-stakeholder-communication] | Turnover, training coordination, owner relations |
| [claims-delay-documentation] | Closeout claims, delay documentation |
Trade Skills
| Skill | Integration Points |
|---|---|
| [mechanical-plumbing-systems] | HVAC commissioning, TAB, plumbing systems |
| [electrical-systems] | Electrical commissioning, emergency power, lighting |
| [fire-protection-systems] | Fire alarm, sprinkler, smoke control, integration |
| [low-voltage-technology] | BAS, security, AV, nurse call commissioning |
| [elevators-vertical-transportation] | Elevator testing, inspection, certification |
| [equipment-division-11] | Kitchen, lab, medical equipment commissioning |
| [sustainable-systems] | Solar, EV, BESS, geothermal commissioning |
| [structural-trades] | Special inspections closeout |
| [building-envelope-exterior] | Envelope commissioning, air/water testing |
| [interior-finishes-trades] | Finishes punch, protection |
| [doors-frames-hardware] | Hardware adjustment, keying schedules |
| [specialties-division-10] | Specialties verification |
| [furnishings-division-12] | Furniture installation, FF&E punch |
| [site-improvements-division-32] | Site punch, landscaping warranty |
| [early-phase-enabling-trades] | Utility closeout, site stabilization |
| [construction-safety-management] | Safety during commissioning activities |
Key PM Actions by Phase
Pre-Substantial Completion (4-8 weeks before SC)
- Verify commissioning pre-functional checklists complete
- Coordinate functional performance testing schedule
- Track commissioning issues log resolution
- Begin self-performed punch walks
- Collect O&M manual submittals
- Schedule owner training sessions
- Verify TAB report completion
- Coordinate final inspections scheduling
Substantial Completion Week
- Complete pre-SC walkthrough with owner/architect
- Document punch list with photos and locations
- Verify life safety systems operational
- Confirm TCO/CO requirements met
- Execute Certificate of Substantial Completion
- Establish warranty start dates
- Distribute punch list to responsible parties
Post-Substantial Completion
- Track punch list completion daily
- Execute owner training per schedule
- Deliver O&M manuals and as-builts
- Coordinate seasonal commissioning testing
- Complete attic stock delivery and inventory
- Execute key turnover and final cleaning
- Collect final lien waivers
Final Completion
- Verify all punch items complete and accepted
- Confirm all documentation delivered
- Obtain permanent Certificate of Occupancy
- Process final payment application
- Release retainage per contract terms
- Close out permits and contracts
Warranty Period
- Respond to warranty callbacks promptly
- Track warranty expiration dates
- Schedule 11-month warranty walk
- Document and resolve 11-month items
- Close out warranties at expiration
Install
Add Commissioning Closeout to your client. Pick the one you use.
npx skills add Construction-Gamma/construction-gamma-skillsInstalls every skill in the repository, then prompts for which to keep.
/plugin marketplace add Construction-Gamma/construction-gamma-skillsAdds the repository as a plugin marketplace; install individual plugins with `/plugin install`.
git clone https://github.com/Construction-Gamma/construction-gamma-skills
cp -r skills/commissioning-closeout ~/.claude/skills/A skill is a plain directory. Copy it into `.claude/skills/` in a project or in your home directory.
Score
69 / 100
Good